The consortium of M/s Bothra Shipping Services Private Ltd (BSSPL) and M/s Ripley & Co. Stevedoring & Handling Private Limited (RSHPL ) jointly won the concession for Mechanization of Existing Berth no. 05 (Erstwhile Berth No. 4B) through a Public Private Partnership (PPP) mode on Design, Build, Finance, Operate and Transfer (DBFOT) basis at the Haldia Dock Complex, Syama Prasad Mookerjee Port, Kolkata. The consortium has formed an SPV, titled Ganges Bulk Terminal Private Limited (GBTPL), journey begins with Award of Concession received on 20th December 2024.
Project Development Progress
Project Photographs
Our Milestone
2024
Concession Agreement Executed between GBTPL and SMPK
2025
Letter of Award (LOA) Issued & Project Site Handed Over
Project Development Initiated under the DBFOT Model
Engineering, Surveys & Regulatory Activities Commenced
2026
Detailed Engineering & Design Activities Reached Advanced Stage
Major Civil Construction Works Commenced Across Terminal Infrastructure
Conveyor Systems, Transfer Towers & Stacker Yard Development Under Execution
2027 (Target)
Commissioning of Stage-I Semi-Mechanized Cargo Handling Operations (TARGET)
2028 (Target)
Completion of Full Mechanization of Berth No. 5 (TARGET)